Whitley Road 4 Reconstruction Update

Rebar - Whitley

Whitley Road 4 Reconstruction Update:
We are beginning the concrete placement for Whitley Road from Hightower Drive to Oakhill Drive on July 27. During this time, there will be days that construction work begins at 4:00 AM. This is being done to allow our contractor to place concrete during the cooler morning period. Concrete placement should not be done during the hotter parts of the day to ensure a quality product.
We apologize for the added noise earlier in the morning. 
THE LIMITS OF THIS PROJECT ARE WHITLEY RD (BUNKER BLVD TO OAK HILL RD).
•   PHASE 1: BEGAN MARCH 23, 2023, THROUGH DECEMBER 2023, WE SHALL CONSTRUCT THE UNDERGROUND UTILITIES AND ROADWAY FROM HIGHTOWER DR TO OAKHILL ROAD WITH WHITLEY RD CLOSED IN THIS AREA. DURING PHASE 1, WE ARE ASKING THE RESIDENTS ON NANCI DR, ROBIN DR, AND KARY LYNN DR S BETWEEN WHITLEY ROAD AND QUAIL RUN TO PLACE THEIR TRASH CARTS ON THE SOUTH SIDE OF SAID STREETS. ANY QUESTIONS SHOULD BE DIRECTED TO JEFF DOWDY WITH FRONTIER WASTE SOLUTIONS AT 940-367-9545 OR UTILITY BILLING AT 817-514-5705. 
Beginning July 27, 2023, concrete paving shall commence from Hightower Drive to Oakhill Drive. This work will start around 6:00 AM on the mornings concrete is being placed.
•   PHASE 2: BEGINNING PENDING, WE SHALL CONSTRUCT THE WHITLEY RD AND HIGHTOWER DR INTERSECTION.
•   PHASE 3: BEGINNING DECEMBER 2023 THROUGH MAY 2024, WE SHALL CONSTRUCT WHITLEY RD FROM BUNKER BLVD TO HIGHTOWER RD WITH WHITLEY ROAD CLOSED IN THIS AREA.